TRAVEL ADVISORY: THRUWAY AUTHORITY ANNOUNCES WINTER SHUTDOWN OF TWO PAVEMENT IMPROVEMENT AND SAFETY ENHANCEMENT PROJECTS ON NEW YORK STATE THRUWAY IN ERIE COUNTY
News originally published by
New York State Thruway AuthorityTRAVEL ADVISORY: THRUWAY AUTHORITY ANNOUNCES WINTER SHUTDOWN OF TWO PAVEMENT IMPROVEMENT AND SAFETY ENHANCEMENT PROJECTS ON NEW YORK STATE THRUWAY IN ERIE COUNTY
Traffic to Return to Normal Patterns on I-90 and I-190
Projects Represent $125.8 Million Investment in Western New York
Work to Resume on Projects in Spring 2027
The New York State Thruway Authority today announced the winter shutdown of two pavement improvement and safety enhancement projects on the New York State Thruway (I-90) and the Niagara Section of the Thruway (I-190) in Erie County. Traffic patterns have returned to normal in both areas of construction for the winter months. These projects represent a combined $125.8 million investment in projects in Western New York.
New York State Thruway Authority Executive Director Frank G. Hoare, Esq. said, “Crews have worked diligently throughout the construction season to make significant progress along two of the busiest corridors in Western New York. We appreciate motorists’ patience as we carry out this critical work. We remain committed to reinvesting toll dollars into infrastructure improvements that enhance safety and provide long-term benefits for everyone who travels the Thruway.”
I-90 Project
The $64 million pavement improvement and safety enhancement project on the Thruway (I-90) in Williamsville, Cheektowaga and Buffalo covers a 6.5-mile stretch in both directions between just east of exit 50 (Niagara Falls – I-290) and exit 53 (Buffalo Downtown – Canada – Niagara Falls – I-190).
During the 2026 construction season, crews completed all drainage improvements, installed a permanent concrete median barrier and increased the vertical clearance of the NY Route 33 overpass to enhance safety and mitigate future bridge strikes.
When construction resumes in spring 2027, crews will focus on extensive pavement repairs to restore the roadway’s structural integrity and improve its long-term durability, followed by the installation of a new asphalt riding surface. Additional safety enhancements include new guiderail, reflective pavement markings and signage.
The project is expected to be completed in late 2027.
Oakgrove Construction of Elma, NY is the contractor for this project.
I-190 Project
The $61.8 million pavement rehabilitation and safety enhancement project on the Niagara Section of the Thruway (I-190) in Cheektowaga and Buffalo covers a 3.5-mile stretch in both directions between exit 1 (South Ogden Street – Dingens Street) and exit 5 (Hamburg Street – Louisiana Street).
During the 2026 construction season, crews completed the first of three phases of the project, beginning at the southern end of I-190 near exit 1. Work included full- and partial-depth concrete pavement repairs, installation of a new asphalt riding surface and bridge improvements. Additional safety enhancements included new overhead lighting, guiderail and signage, as well as repairs to drainage structures.
When construction resumes in spring 2027, crews will begin the second phase, continuing north along the I-190 corridor. The third and final phase will begin in spring 2028, with work progressing toward exit 5.
The project is expected to be completed in late 2028.
Union Concrete & Construction Corp. of West Seneca, NY is the project contractor.
Automated Work Zone Speed Enforcement Program
The Thruway Authority utilized New York State's Automated Work Zone Speed Enforcement (AWZSE) program throughout the 2026 construction season to enhance safety for highway workers and motorists traveling through the I-90 and I-190 construction zones.
During enforcement deployments within the two project areas, more than 1.1 million vehicles were monitored and 30,251 Notices of Liability (NOL) were issued, including 25,044 on I-90 and 5,207 on I-190.
Governor Kathy Hochul signed the program into law in 2021. It is designed to encourage motorists to slow down, obey posted speed limits and exercise caution when traveling through active construction zones.
About the New York State Thruway Authority
Built in the early 1950s, the Governor Thomas E. Dewey Thruway is one of the oldest components of the National Interstate Highway System and one of the longest toll roads in the nation. It sets the standard for modern highway geometric design with safe roadway characteristics including smooth curves, wide medians and unobstructed driver sight distance.
Year after year, the Thruway system is recognized as one of the safest highways in the nation. In 2025, the Thruway-wide fatality rate was 0.36 fatalities per 100 million vehicle miles traveled, approximately 45 percent lower than the nationwide five-year average fatality rate of 0.65 for Interstate highways.
###
Legal Disclaimer:
EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.